2017 Street Project
Shafer Street Project
The City of Shafer is in the process of preparing plans and specifications for a Street Improvements Project in your neighborhood.
Project Scope:The primary purpose of this project is to eliminate aging streets and culverts along with hydrant replacement. The city has pursued state and federal funding opportunities; however, the project does not qualify.
Project Schedule:
Neighborhood Meeting** January 23, 2017 - 5-7pm
Bidding March, 2017
Award Contract April, 2017
Commence Construction May, 2017
Project is scheduled to begin the week of May 8, 2017
Right-of-Way Trees starting to be removed May 4, 2017
Click here for Dresel letter re: Mailboxes during Construction
Complete Construction October, 2017
**This is a public informational meeting to discuss street and utility improvements that the City is proposing as part of the 2017 Street Improvements project along
302nd Street, 303rd Street, Regal Avenue South, and Ridgewood Avenue (North & South).
Project Contacts:
Jon Herdegen, City Engineer 612-548-3124 jherdegen@msa-ps.com
Lucas Jones, Project Engineer 612-548-3126 ljones@msa-ps.com
Dan Vogel, Mayor 651-257-6228 danv.shafermn@gmail.com
City Public Works Director 651-257-4726 publicworks@shafermn.com
Advertisement for Bids:
Disclaimer: the City of Shafer is not responsible for content of linked-to websites that take you off the City's website pages.
The City of Shafer is in the process of preparing plans and specifications for a Street Improvements Project in your neighborhood.
Project Scope:The primary purpose of this project is to eliminate aging streets and culverts along with hydrant replacement. The city has pursued state and federal funding opportunities; however, the project does not qualify.
Project Schedule:
Neighborhood Meeting** January 23, 2017 - 5-7pm
Bidding March, 2017
Award Contract April, 2017
Commence Construction May, 2017
Project is scheduled to begin the week of May 8, 2017
Right-of-Way Trees starting to be removed May 4, 2017
Click here for Dresel letter re: Mailboxes during Construction
Complete Construction October, 2017
**This is a public informational meeting to discuss street and utility improvements that the City is proposing as part of the 2017 Street Improvements project along
302nd Street, 303rd Street, Regal Avenue South, and Ridgewood Avenue (North & South).
Project Contacts:
Jon Herdegen, City Engineer 612-548-3124 jherdegen@msa-ps.com
Lucas Jones, Project Engineer 612-548-3126 ljones@msa-ps.com
Dan Vogel, Mayor 651-257-6228 danv.shafermn@gmail.com
City Public Works Director 651-257-4726 publicworks@shafermn.com
Advertisement for Bids:
- 2017 Street Improvement, sealed bid requests - until 2:00pm, March 27, 2017 - click here for details
- March 28, 2017, 6pm - Street Committee Meeting for Review of Project Scope & Bids - Notice of possible Quorum
Disclaimer: the City of Shafer is not responsible for content of linked-to websites that take you off the City's website pages.